Quality Matters

Say Goodbye 
to Concrete Cold Joints

A look at cold joints in concrete and how to prevent them


By Tim Kampert February 4, 2021
Work in progress on a slab-on-grade concrete foundation with rebar and poured concrete
A concrete crew fills the footing form for a slab-on-grade home. The risk of pouring all of the footings first is that they will begin to set before the concrete for the slab arrives, usually resulting in cold joints. | Photos: courtesy IBACOS
This article first appeared in the February 2021 issue of Pro Builder.

Concrete cold joints are common in residential construction. I probably see them on about 75% of the slabs I inspect, as well as in plenty of foundation walls. Cold joints can sometimes wick water into the home, but even without water intrusion issues, their appearance screams “shoddy work” to the homeowner. The problem is easy to avoid if you stop to think about how concrete cures.

Honeycombing on a concrete footing
DON'T: Wait too long between pours. An unsightly area of exposed aggregate—a condition known as waffling or honeycombing—is the product of waiting too long between pours, making it impossible to properly intermix the concrete layers and creating a cold joint.

 

What Causes Cold Joints in Concrete?

A cold joint is a sign that too much time elapsed between successive concrete pours. Imagine, for instance, that a concrete crew fills the footing form for a slab-on-grade home (main image, above) or places the first lift of concrete for a foundation wall. If they don’t pour the slab or the second lift soon enough, that first batch of concrete may begin to dry, preventing it from properly intermixing with successive batches.

Cold joints are easy to spot. Some appear as long cracks or discolorations (see photo, below). Others show up as honeycombing or areas of exposed aggregate (see photo, above) caused by a poor mix that prevents the fines (very small aggregate or dust) in the concrete from moving and encapsulating the aggregate as it should.

In a foundation wall, rebar generally prevents cold joints from becoming a structural issue. But with a slab-on-grade home, the lack of vertical steel means a cold joint can become a weak spot. 

Dark cold joint on concrete foundation
DON'T: The cold joint in this concrete wall shows up as a dark, diagonal line. 

How to Prevent Cold Joints in Concrete

There are a couple of ways to prevent cold joints. In hot weather, a retarding admixture can slow the drying process. And, of course, properly vibrating the concrete after each pour will help the different layers mix and prevent honeycombs from forming.

However, an admixture will only slow the drying process for a short time. It’s still important to pour the second batch as soon as possible; otherwise it may be too late to stop a cold joint, even if you use a vibrator. 

How do you know when it’s too late? Simply, if the concrete surface has started to glaze over that means the pour has begun to set. 


RELATED


When pouring slabs in hot climates, such as in Florida, some crews will water down the mix from a 4 or 5 slump to 6 or 7. Although this slows drying and makes the concrete easier to work, that added water can make the cured concrete more porous and reduce its overall strength, potentially allowing for cracks to form. If the slab is to receive a sealed finish—something not uncommon in garages—that porosity will make the finish less predictable. Again, that problem is mostly one of customer perception, but it should not 
be discounted.

Simultaneously pouring the concrete slab and footing is a best practice that avoids cold joints
DO: The proper sequence for a slab-on-grade home is to pour the footing and slab monolithically, working from one end of the house to the other.

 

Cold-Joint Solution: Manage the Concrete Pour

The proper solution is obvious: You need to make sure your concrete provider has enough trucks to eliminate waiting between batches. However, the way the crew places the concrete also matters, especially for slab-on-grade foundations.

Most structural engineers specify that the slab and footing be placed at the same time, but crews sometimes ignore that. Instead, they pour the concrete from the first few trucks into the footing forms, then use the concrete from the next few trucks for the slab. It’s easier for crews to work the concrete this way, but by the time they get to the slab, the footing has already started to dry. 

The correct sequence is to pour the footing and slab monolithically, moving from one end of the house to the other. It will take a bit more effort to work the concrete into the forms, but cold joints will be far less likely.

Tim Kampert drives quality and performance in home building as a building performance specialist on the PERFORM Builder Solutions team at IBACOS.

 

Advertisement
leaderboard2 - default

Related Stories

Q+A

Soil Connect Is Moving Dirt and Building Relationships

Cliff Fetner created Soil Connect so builders and developers could more easily move dirt and other aggregates from jobsite to jobsite, but it has expanded to become something much more

Building Materials

Construction Material Prices Fell for the Second Straight Month in April

Construction input prices are falling after the pandemic’s historic inflation rates, and these materials are seeing the biggest annual price changes

Building Materials

Led by Ready-Mix Concrete, Building Materials Prices Inch Higher

Ready-mix concrete prices are rising at a historic pace, and prices for other commonly used building materials aren't far behind

Advertisement
boombox1 -
Advertisement
native1 - default
halfpage2 -

More in Category

Delaware-based Schell Brothers, our 2023 Builder of the Year, brings a refreshing approach to delivering homes and measuring success with an overriding mission of happiness

NAHB Chairman's Message: In a challenging business environment for home builders, and with higher housing costs for families, the National Association of Home Builders is working to help home builders better meet the nation's housing needs

Sure there are challenges, but overall, Pro Builder's annual Housing Forecast Survey finds home builders are optimistic about the coming year

Advertisement
native2 - default
Advertisement
halfpage1 -

Create an account

By creating an account, you agree to Pro Builder's terms of service and privacy policy.


Daily Feed Newsletter

Get Pro Builder in your inbox

Each day, Pro Builder's editors assemble the latest breaking industry news, hottest trends, and most relevant research, delivered to your inbox.

Save the stories you care about

Lorem ipsum dolor sit amet lorem ipsum dolor sit amet lorem ipsum dolor sit amet.

The bookmark icon allows you to save any story to your account to read it later
Tap it once to save, and tap it again to unsave

It looks like you’re using an ad-blocker!

Pro Builder is an advertisting supported site and we noticed you have ad-blocking enabled in your browser. There are two ways you can keep reading:

Disable your ad-blocker
Disable now
Subscribe to Pro Builder
Subscribe
Already a member? Sign in
Become a Member

Subscribe to Pro Builder for unlimited access

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua.