Construction projects are complex in nature and prone to cost and schedule overruns. A significant factor that often contributes to such overruns is rework.
Rework is defined as the ‘unnecessary effort of redoing a process or activity that was incorrectly implemented the first time.’
Design changes, errors and omissions account for 79% of the total rework costs in a project.
Omissions are caused by the following failure types:
Here's a breakdown of failure types in omissions:
- Violations 60%
- Slips 16%
- Lapses 15%
- Mistakes 8%
About the Author
Denis LeonardDenis Leonard
Denis Leonard has a degree in construction engineering, and an M.B.A. and a Ph.D. in quality management. He is a Fellow of the American Society for Quality and has been an Examiner for the Baldrige National Quality Award Board of Examiners, a Judge on the International Team Excellence Competition, and a Lead Judge on the National Housing Quality Award. He has experience as a quality manager in the home building industry as well as construction engineer, site manager, and in training, auditing, and consulting with expertise in strategic and operational quality improvement initiatives. His work has achieved national quality, environmental, and safety management awards for clients.